What is the critical path?
A. The path from resource to task that passes through all critical components of a project plan
B. The path between tasks to the projects finish that passes through all critical components of a project plan
C. The path from start to finish that passes through all the tasks that are critical to completing the project in the shortest amount of time
D. The path from start to finish that passes through all the tasks that are critical to completing the project in the longest amount of time

Respuesta :

CPED

Answer:

Option C. The path from start to finish that passes through all the tasks that are critical to completing the project in the shortest amount of time

is the correct answer.

Explanation:

  • Critical path is the term used in Project management.
  • It can be known by determining the longest stretch for dependent activities and the time required for them to complete.
  • A method known as "critical path method" is used for Project modelling.
  • All types of projects including aerospace, software projects, engineering or plant maintenance need Critical method analysis for the modeling of project and estimation.

I hope it will help you!