Tyrone, a project manager at a computer firm, needs to monitor the schedule of a critical project. What should Tyrone do first?

A. Develop a schedule baseline
B. Calculate all schedule variances
C. Identify major scope creep
D. Analyze the completion status of activities

Respuesta :

Answer:

The correct answer is letter "C": Identify major scope creep.

Explanation:

Scope creep in project management refers to those uncontrolled changes in the scope of a plan. This can be caused when the scope of the project is not defined or controlled correctly. It may cause schedule variances so it is important to deal with it during the first steps of monitoring a critical project.