Suds and Duds Laundry washed and pressed the following number of dress shirts per​ week:

Week Work Crew Total Hours Shirts
1 Sud and Dud 24 168
2 Sud and Jud 46 130​
3 Sud, Dud, and Jud 62 162
​4 Sud, Dud, and Jud 51 125
5 Dud and Jud 45 131

Required:
For the given​ information, the labor productivity per hour for each week is ​(enter your responses rounded to two decimal ​places)​:________

Respuesta :

Answer and Explanation:

The computation of the labor productivity per hour for each week is shown below:

As we know that

Labor productivity = Total shirts ÷ Total hours

For week 1

= 168  ÷  24

= 7 shirts per hour

For Week 2

= 130  ÷  46

= 2.83 shirts per hour

For Week 3

= 162  ÷  62

= 2.61 shirts per hour

For Week 4

= 125  ÷  51

= 2.45 shirts per hour

For Week 5

= 131  ÷  45

= 2.91 shirts per hour