Respuesta :

Answer:

Step-by-step explanation:

Required man days to complete the job = 8 * 6

                                                                   = 48 Man Days

Required labors to complete the job by 15 days = 48/15

                                                                               = 3.2

It means, it is required 4 labors can complete the certain work by 15 days