Mariott Condominium, located near San Diego, California, plans to renovate its main building. The project will begin April 1, and the goal is to complete by August 1 (in 17 weeks). The condominium manager identifed the renovation activities and their estimated time below.
a) Draw a project network. You may want to draw on paper then do it here by connecting the given nodes with arcs (i.e, arrows). You might not use all of the given arcs.
b) What are the critical activities?
c) What activity has the most slack time?
d) Will the project be completed by August 1?