Job 593 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $2,461 Direct labor-hours 74 labor-hours Direct labor wage rate $ 18 per labor-hour Machine-hours 137 machine-hours The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $19 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 593 would be:(A) $3,720(B) $3,793(C) $7,236(D) $6,396

Respuesta :

Answer:

The correct answer is D: $6,396

Explanation:

Giving the following information:

Direct materials $2,461

Direct labor-hours 74 labor-hours

Direct labor wage rate $ 18 per labor-hour

Machine-hours 137 machine-hours

The Corporation applies manufacturing overhead based on machine-hours.

The predetermined overhead rate is $19 per machine-hour.

Total cost= direct material + direct labor + manufacturing overhead

TC= 2461 + 74*18 + 137*19= $6,396