What is the typical impact on a program's cost and schedule when unstable requirements lead to changes late in the system's development?[Identify how instability of requirements, design, and production processes impact program cost and schedule.]

a. Significantly negative impact on cost and schedule
b. Marginally negative impact on cost and schedule
c. Negative impact on cost; no impact on schedule
d. No impact on cost; negative impact on schedule

Respuesta :

Answer: The correct answer is "a. Significantly negative impact on cost and schedule".

Explanation: The typical impact on a program's cost and schedule when unestable requirements lead to changes late in the system's development is the significantly negative impact on cost and schedule.