Overallocated manufacturing overhead results when A. actual overhead is less than expected. B. production is less than last year. C. estimated overhead is less than actual overhead. D. actual overhead is less than allocated overhead.

Respuesta :

Answer:

D. actual overhead is less than allocated overhead.

Explanation:

The over allocated manufacturing overhead equals to

= Applied overhead or allocated overhead - actual overhead

When the applied overhead or allocated overhead is more than the actual overhead than it would be over allocated manufacturing overhead

And, if the applied overhead or allocated overhead is less than the actual overhead than it would be under allocated manufacturing overhead