Jackson High School formed several teams to plan and execute the 150th anniversary celebrations of the school. Over a period of two months, the teams organized events, oversaw logistics and coordinated student activities. The events that were planned were on a large scale and required a lot of input from the teachers and students. This is an example of a(n) _________ team.A. project
B. management
C. work
D. action
E. parallel

Respuesta :

Answer:

project team

Explanation:

The members belong to different groups (teacher and students)

They have difference functions and and they were dividend into sub-temas (one for each event)

And specially, after the celebration of the 150th annyversary ended the team are disbanded as the project is complete.

The student and teachers worker together for the goal of the 150th anniversary party.