Project scheduling involves all of the following EXCEPT ____. Group of answer choices arranging for necessary resources assigning specific tasks to team members defining project constraints staffing the project team

Respuesta :

Answer:

staffing the project team

Explanation:

Project scheduling involves all the activities that make delivering a project efficiently and on time possible. The project schedule functions as a tool that tells the story or communicates the work that needs to be performed, what resources are required to perform this work and how long or what time this would consume. This schedule typically shows start and finish dates, reflecting all of the work associated with delivering the project on time. However it does not include staffing the project team.