A new CEO has come into your company and has promptly shut down your project because it no longer met the business needs of the company. While not pleased with the decision, you document the level and completeness of the project to date. What activity or process is this part of? a. Close Project or Phase b. Control Scope c. Validate Scope d. Close Procurements

Respuesta :

Answer:

a. Close Project or Phase.

Explanation:

Close project occurs when the activities of the project is finalised, information is archived or documented, and resources are released to be used in new endeavours.

Project closure involves 3 activities final project housekeeping, project review, and project close-out report.

The process of documenting the level of project completeness when shutting down the project is part of close project phase.