Which of the following is an output of Project closure? a. Agreements Closure Procedure b. Administrative Closure Procedure c. Final Product, Service, or Result d. None of the above

Respuesta :

Answer: C

Explanation:

Close Project is the process of giving finishing touches to every activities involved in the project. The key benefits of "close project" are that the project information is archived for future use, completion of the planned work and the release of organizational team resources to take part in new endeavors. The process can performed once or at every stage in the project.

An output of project closure is product, service, or result. Once the product or result has been achieved, it may be handed to a different group that will operate, support and maintain the product during its life cycle. The output is the final product, result or service that the project was meant to produce.