Respuesta :

Answer:

[tex]Y=12.2 \frac{gpm}{ft}[/tex]

Explanation:

Hello!

In this case, since we can find that the well produces 280 gpm, and the given drawdown is 23 ft, we need to divide 280 by 23 to obtain the yield in gmp/ft as shown below:

[tex]Y=\frac{280gpm}{23ft} \\\\Y=12.2 \frac{gpm}{ft}[/tex]

Best regards!