contestada

Strohrmann, a large-scale bakery in Pennsylvania, is laying out a new production process for their packaged bread, which they sell to several grocery chains. It takes 10 minutes to bake the bread. How large an oven is required so that the company is able to produce 3859 units of bread per hour

Respuesta :

Answer:

See below

Explanation:

Given the above information, computation of quantity of the oven is seen below;

Inventory = flow rate × Flow time

Inventory = 3,859 units per hour × 10 minutes × 1 hour / 60 minutes